CRONOSProcess Historian
Deployment

From first contact to the first shift report

An Edge installation takes 1 to 2 days on site; Server with redundancy, 3 to 5. The sequence below is the one we follow on every deployment.

Survey

Which PLCs, protocols and SCADAs exist, how many variables matter, how the plant closes the shift today. A 30 to 60-minute conversation with automation and operations.

Remote · CRONOS + customer

Controller access

Fixed IPs, open ports, PUT/GET or OPC UA enabled on Siemens. Network probe and read test before any data is stored.

On site · customer automation

Installation

Setup on the server, service running, variable catalogue generated from the PLC project or the OPC UA server. First start with the real sources.

On site · CRONOS

Process configuration

Areas, overview, alarms, production counters and shifts, maintenance assets, process rules. Done with the people who know the plant.

On site · CRONOS + operations

Users, backup and e-mail

Roles, password policy, automatic backup, customer logo on reports, supervisor list and automatic delivery configured and tested.

On site · CRONOS + IT

Acceptance and follow-up

Acceptance checklist with operations, licence activated, 30 days following the reports to adjust criteria and factors with real data.

Remote · CRONOS

What we ask for beforehand

  • List of PLCs with make, model and IP
  • PLC project or tag list, if available
  • Recipes, steps and equipment names
  • How the shift is closed today (spreadsheet, bulletin)
  • Company logo and the list of report recipients

What we deliver

  • Server running with automatic backup
  • Screens configured for the plant
  • Automatic shift report by e-mail
  • User manual and installation guide
  • Updates during the support period

After deployment

Updates arrive as a package that preserves the database and configuration, no reinstall. Criteria changes are applied by script, with a copy of the previous file and a record in the system.

Want to see CRONOS reading your PLC?

In 30 minutes we can tell whether your plant is ready and how soon the first shift report lands in your inbox.